05/26/2021
News & Updates
06/05/2018
June 2018 Project Update
Crews installed five large girders over Curlew Drive on Saturday, June 2, completing the operation just before heavy rain moved in.
April 2018 Project Update
03/08/2018
LOOK AHEAD: FIRST 90 DAYS OF CONSTRUCTION ON PHASE II
VIRGINIA BEACH – As construction begins on Phase II of the I-64/I-264 Interchange Improvements, expect to see activity over the next few months in the following areas. Lane closures, shoulder closures and/or flagging operations will be used to accomplish the following work as necessary:
02/08/2018
Steel Girder Installation Begins
Steel girder placement began the week of Feb. 5 near Newtown Road Ramp 15A. These girders will support the new collector-distributor lanes that will serve vehicles traveling from I-264 east and I-64 to the Newtown and Witchduck road interchanges.
Read article
12/07/2017
Phase II Contract Awarded to Improve I-264 East in Virginia Beach
The Commonwealth Transportation Board (CTB) awarded a $105.4 million contract on Dec. 6 to construct Phase II of the I-64/I-264 Interchange Improvements Project.
The contract was awarded to The Lane Construction Corporation of Cheshire, Conn., to improve mobility, reduce congestion and increase safety on I-264 east from Newtown Road in Norfolk to Witchduck Road in Virginia Beach. This project is Phase II of the I-64/I-264 Interchange Improvements. It is scheduled to be complete in the fall of 2021
Lane Construction Corp. will build a new collector-distributor road and reconfigure the south side of the interchanges at Newtown and Witchduck roads. The new ramp configurations will remove the weaving traffic movements that eastbound motorists encounter at both interchanges when they exit and enter the interstate. The project will also build a bridge over I-264 connecting Greenwich Road on the south side to Cleveland Street on the north.
The project is funded by SMART SCALE and the HRTAC. For updates on Phase I and II of the I-64/I-264 Interchange Improvements work, subscribe here.
Read article
10/31/2017
Bridge Piers Completed Between Kempsville and Newtown Roads; Steel Girders Up Next
05/31/2017
MAY PROJECT UPDATE
High-Voltage Transmission Line Work Over I-64 Prepares Way For New Ramp
03/03/2017
DEMOLITION OF I-64 SOUND WALL TO BEGIN SOON
Read the notice delivered to nearby residents.
01/31/2017
JANUARY PROJECT UPDATE
NORFOLK – Construction of the first of the I-64/I-264 Interchange Improvements projects is well underway, with clearing operations and other work visible from the interstate. Read more about the early progress and what to expect in the weeks ahead.
09/21/2016
CTB AWARDS CONTRACT FOR I-64/264 RAMP IMPROVEMENT
VIRGINIA BEACH – The Commonwealth Transportation Board (CTB) today awarded a construction contract worth nearly $107.4 million to Tutor Perini Corporation of New Rochelle, NY, to expand and improve the ramp from I-64 West near the Twin Bridges to I-264 East and Newtown Road.